Factory acceptance test checklist for packaging machinery

Ganesh HSStrategy and Technology, GullySystem
Practical advice · 5 min read

In this guide 6 sections
The short answer

A packaging machine FAT checklist lists the product runs, rated speed, reject counts, changeover time, safety checks and sign-offs to record before the line leaves. Fix the product, film or carton, and run length beforehand, and have the customer sign each result on the day.

Agree the test conditions before the day

A packaging line behaves differently on every film, carton and product. Settle the test material first. Name the film grade or carton board, the product, the fill weight or count, and the pack size to be run.

Ask the customer to send enough of their own material. A trial on your substitute proves little if the customer’s laminate is slipperier or their product is stickier.

Write down the rated speed in packs per minute, the run length for each test and the reject limit. These three numbers decide whether the day ends in a signature or an argument. Record the room conditions as well, since humidity and temperature change how film sticks and how cartons feed.

  • Film, carton or pouch material supplied
  • Product and fill weight or count
  • Rated speed in packs per minute
  • Length of each timed run
  • Reject limit agreed in writing

Record the runs, not just the result

One good minute proves nothing. Run the machine for the agreed period at the rated speed and log the packs made, the packs rejected and every stoppage with its cause. A film splice, a jammed carton and a sensor trip are different problems.

Repeat at a lower and at a higher speed if the contract allows a range. The numbers show where the machine begins to struggle. A line that holds its reject rate at rated speed but drifts at a faster setting tells the customer how much headroom they really bought.

Capture seal quality too. Check seal strength, leak test result, print registration, code and date print, and pack weight against the checkweigher.

Time the changeover and the cleaning

Customers buy a packaging machine for a mix of formats, so a changeover deserves its own test. Change from one format to another with the operator the customer will use. Time it with a stopwatch.

Note each step: change parts swapped, guides reset, recipe selected, first good pack. Record who did what.

For food and pharma lines, add a wash-down or cleaning step. Check that guards come off with the tools supplied and that nothing traps product. A forming collar that needs a hammer to remove will cost the customer hours every week.

Check safety, controls and documents

Press every emergency stop and test every interlock on the guards. Confirm the light curtain stops the machine within the distance the risk assessment states. Record the result for each.

Open the HMI screens next. Check alarm messages, recipe storage, user levels and the counters for good and rejected packs. Take a backup of the PLC and HMI programs and note the version.

Hand over the draft manual, electrical drawings, spares list and lubrication chart, or note which are still pending.

  • Emergency stops and guard interlocks
  • Light curtain stopping distance
  • Alarm list and recipe storage
  • User levels on the HMI
  • PLC and HMI backup version noted

Close the day with sign-off and a punch list

List every item that failed or was waived. Give each one an owner, a deadline, and the place where it will be fixed, whether before dispatch or at site. The customer signs the sheet and keeps a copy.

Photograph the nameplate, the panel and the final run counters. Do it before the crate closes. Keep the shots in the same folder as the signed sheet, so a later warranty claim can be checked quickly. File them with the signed sheet against the machine’s serial number.

Before your next FAT, print this checklist and cross out any line your machine cannot honestly pass. Fix the contract wording or the machine before the customer visits. Add the sheet to your quote pack as well, so the customer sees the test before they buy.

Packaging FAT record sheet

A two-sided sheet. The front holds the test conditions: material, product, rated speed and reject limit. Below them sits a table of timed runs with columns for packs made, packs rejected and stoppages with cause. The back holds the changeover timings, safety checks, document handover list, punch list and signature blocks for both parties.

Open a blank worksheet to print

Questions owners ask

How long should each timed run be?

Agree it in the contract. Long enough to include normal stoppages such as a film splice, but short enough to finish in a day. Many builders run at least one continuous period per speed.

Should the customer bring their own product?

Yes, where possible. Their product and packing material reveal sticking, dusting, slip and sealing problems that a substitute may hide. Agree quantities well before the visit.

What counts as a reject?

Define it beforehand: a poor seal, a missing code, a wrong weight or a damaged pack. The checkweigher, vision system or manual check that detects it should be named in the sheet.

What if the machine fails part of the FAT?

Log the failure on the punch list, naming who fixes it and by when. Agree whether a retest is needed, or whether the item can be closed at site commissioning, before the customer signs.