Project document control: revisions, transmittals and approvals

Ganesh HSStrategy and Technology, GullySystem
Practical advice · 4 min read

In this guide 6 sections
The short answer

Project document control is a register that lists every drawing or document with its revision, the people who received it, who approved it and which version reached site. Add a transmittal for each issue and a folder structure that keeps superseded files out of reach of the site team.

What does the document register hold?

One row per document. The row carries a unique number, title, discipline, current revision, status and date of last issue. The number never changes, even when the title is reworded.

Each revision gets its own line beneath. A structural drawing might move from Rev A for comment to Rev B for tender and Rev C for construction. Reason for change goes beside each step.

Keep the register in one place. When the architect, the engineer and the contractor each hold a private list, three versions of the truth appear and the argument starts at the next site meeting.

  • Document number and title
  • Discipline and originator
  • Revision letter and date
  • Status code, such as for comment or for construction
  • Superseded by, when replaced

Why does every issue need a transmittal?

A transmittal is the cover note that proves what was sent, to whom and when. Without it, a contractor can say a revised ductwork drawing never arrived, and nobody can prove otherwise.

List each document on the transmittal with its revision and reason for issue, then name the recipients, the response needed and the date it is due. Simple, yet often skipped.

Number transmittals in sequence. Gaps in the sequence show a missing record, and replies can quote the number rather than describe a parcel of PDFs.

How should approvals be recorded?

Approval belongs on the revision, not on the document in general. Approved at Rev B says nothing about Rev C. Record the reviewer, the date and the code returned, such as approved, approved with comments or rejected.

Set a response period at issue time. Silence is a risk. A shop drawing sitting with the consultant for three weeks delays steelwork, and the register should flag it by name.

Keep comments attached to the revision they refer to. A marked up PDF returned by email is easily lost, and the next revision then repeats the same mistake.

  • Reviewer and organisation
  • Return code and date
  • Comments file for that revision
  • Reissue due date

How do you know which version was used on site?

Mark a revision as received on site. A site engineer scans a QR code or ticks a field when the printed set is replaced. Old prints are collected and stamped superseded. Do it the same day.

This matters when a slab is poured to Rev B while Rev C moved a column. The register then shows the date Rev C reached site, the date of the pour and who signed the pour card.

Run a weekly check. List every drawing and specification issued in the last week that is not yet confirmed on site, and chase the site engineer for each one.

What should the folder structure look like?

Mirror the register. Top level by project, then discipline, then document type. Inside each, keep a Current folder and a Superseded folder. Site staff see only Current.

Name files with the document number, revision and a short title. Nobody should rename a file to final or latest.

Limit who can upload to Current. Use permissions so only the document controller moves a file there, after the register entry is updated.

Document register template

Register template. One tab holds columns for document number, title, discipline, revision, status, issue date, transmittal number, recipients, approval code, approval date and date confirmed on site. A second tab holds a transmittal cover note with a recipient list and a response due date.

Open a blank worksheet to print

Questions owners ask

What is the difference between a revision and a version?

A revision is a formal issue that others may rely on, like Rev B. A version is a working save inside the author’s file. Only revisions go in the register.

Who runs document control on a project?

A document controller, often supported by an assistant project manager. Small projects may give the role to one coordinator, but it still needs a named owner.

Do small projects need a register?

Yes, if more than one party issues drawings. A simple sheet is enough at first. Move to software when approvals and site confirmation become hard to chase.