Documents to attach to a running bill at a Durgapur or Asansol plant

Ganesh HSStrategy and Technology, GullySystem
Practical advice · 5 min read

In this guide 6 sections
The short answer

Attach the work order and its amendments, the signed measurement sheet, the attendance and wage sheet, the safety permits and the gate pass records. Track the set bill by bill, so one missing sheet is spotted before submission and does not hold up the payment of the whole running bill.

Why one missing sheet stops the whole bill

A running bill at a steel plant or colliery is checked by several desks. The engineer verifies quantities, the safety officer looks at permits and the contracts section matches the work order. Accounts then releases the money.

Each desk can return the bill. When a desk finds one sheet absent, the entire bill goes back, and the contractor waits for the next cycle. Weeks pass for want of one signature. That is a poor trade.

Treat the document set as part of the bill. Not an afterthought.

The core set for every running bill

Start with the work order and every amendment, since the rate and scope on the bill must match the latest one. Add the signed measurement sheet, which should reference the same item numbers as the schedule of rates. If a quantity exceeds the order, the approval for excess work belongs here too.

Next comes the labour side. Attach the attendance register for the period, the wage sheet and the proof of statutory deposits that your principal employer asks for. A plant in the Durgapur belt will usually insist on this before it releases payment for manpower supply.

Finally, attach the material side where it applies, such as challans for steel or cement issued by the plant and the reconciliation of stores.

  • Work order with all amendments and approvals for extra items
  • Measurement sheet signed by the plant engineer
  • Attendance register and wage sheet for the bill period
  • Proof of statutory deposits for the workforce
  • Store issue and return slips if material came from the plant

Safety and gate records that get forgotten

Plants and collieries care about permits as much as quantities. A hot work permit, a confined space entry permit or a height work permit may be needed for each job in the bill. The safety officer will ask for them even when the engineer has already signed the measurements.

Gate records are the second blind spot. Vehicle entry passes, worker gate passes and tool movement slips prove that the men and machines were on site. In Asansol collieries, where entry is controlled tightly, a bill that lists forty days of work but only twenty days of gate passes will be questioned.

Keep originals at site. Attach copies, tagged with the bill number.

Track documents by bill, not by folder

A shared folder with names like final2 and signed_new is where sheets go missing. Instead, give each running bill a record with a fixed list of required documents. Each line has a status: not received, received, signed or returned with a remark.

The accounts manager then sees at a glance that bill 14 lacks the safety permit for week three, while bill 13 is complete and can go today. Bills move on their own. One gap no longer holds up the rest.

A software register that stores scans against each line, with the name of the plant officer who signed, also gives you evidence when a payment is questioned months later.

  • One record per running bill with a required document list
  • Status for each document and the date it changed
  • Scan stored against the line, with the signing officer
  • Alert when a bill has gaps three days before submission

A checklist to start with this week

Pick the bill that was returned most recently and list every document the plant asked for. Add them to a one page checklist and keep it with the next bill’s file.

Ask your site supervisor to tick each line as the paper arrives, not on the day of submission. A gap found on day five costs a phone call. The same gap found at the plant gate costs a cycle.

Running bill document checklist

A printable checklist kept for every running bill. Rows list the work order and amendments, measurement sheet, attendance register, wage sheet, statutory deposit proof, safety permits, gate passes and store slips. Columns give status, date received, signing officer and a remark for what is missing.

Open a blank worksheet to print

Questions owners ask

Do all plants ask for the same documents?

No. Each plant and colliery has its own contracts section and checklist. Ask the contracts desk for their current list and build your checklist from it, not from another contractor’s.

Who should sign the measurement sheet?

The plant engineer named in the work order, usually along with your site representative. Joint measurement on the day avoids later disputes over quantities.

Can scanned copies replace originals?

Some plants accept scans for the first check and want originals at final settlement. Confirm with the contracts desk and keep both versions linked to the same bill record.

What should we do when a bill is returned?

Record the reason against the specific document, fix only that item and resubmit. Do not re-prepare the whole bill, which risks new errors.