Low Spindle Utilisation in a Machine Shop: Finding the Lost Hours

Ganesh HSStrategy and Technology, GullySystem
Practical advice · 4 min read

In this guide 6 sections
The short answer

Low spindle utilisation rarely comes from machines running slowly. It comes from idle gaps between cycles: setups that run long, jobs waiting for material, programmes being proved on the machine and parts queued at inspection. Booking every stoppage against a reason code shows which gap is largest.

Separate idle time from slow cutting

A spindle that turns for four hours of an eight hour shift is not cutting slowly. It sat still for the other four. The first job is to account for that stillness.

Feeds and speeds matter. They are a later question. Most shops find their largest loss sits between jobs, not inside them.

Ask each operator to book start and end of every state against the job card: setup, run, waiting and breakdown. Start with one week and a few machines.

Setup time hides the most hours

Setup includes fetching the fixture, loading the offsets, touching off tools and running a first piece. On a VMC with a vise, it may be short. On a five-axis part with a dedicated fixture and a probing routine, it can take the morning.

Compare booked setup against the planned figure on the route card. A repeat part that takes twice the planned setup tells you something is missing, perhaps a fixture without a locating pin or offsets that were not saved.

Fix the repeat parts first. They return every month. Each fix pays again, and a single missing locating pin can cost a half hour on every run.

  • Fixture not at the machine when the job starts
  • Tool offsets re-entered instead of recalled
  • First piece waiting for the inspector
  • Collets or soft jaws changed with no prepared set

Waiting for material is a planning fault

A lathe that stops because bar stock has not arrived looks like a purchasing problem. Often the cause is earlier: a job released with no check on whether the bar, the casting or the heat treated blank was in the stores.

Look at the booked waiting hours by reason. If material heads the list, check the release step. Does the planner see stock and incoming orders before sending the job to the floor?

Outside processes add another gap. Parts out for plating or heat treatment come back late and leave the next operation idle.

Programme proving and inspection queues

A new G-code programme proved on the machine ties up a spindle that could be cutting. Where possible, prove it in simulation or on the least busy machine. Record how long each proof takes so you can see the true cost of new parts.

Inspection queues grow when one inspector serves six machines. The operator waits for first piece approval with the spindle idle. Count the minutes between asking and approval, per job.

Both losses are visible once the stoppage is booked with a reason. Without a reason, they all fall into one vague bucket called downtime.

  • Minutes from first piece offered to approval
  • Programme proving hours per new part number
  • CMM or gauge room queue at shift start
  • Rework loops after a failed first article

Turn booked hours into one weekly review

Add the booked hours by reason for each machine. Rank the causes. The top two will usually account for most of the lost time, and they differ from shop to shop.

Take the ranked list to a short Monday meeting with the planner, the tool crib and the inspector. Choose one cause and one fix. Run it for two weeks, then look at the figures again.

Software helps by capturing the bookings at the machine and totalling them, so no one compiles a sheet. Start by trialling the reason codes on a paper card for a week.

Spindle hours loss log

A log sheet, a row for each machine and shift. Columns: job number, planned hours, then booked hours under setup, waiting for material, programme proving, inspection queue, breakdown and other. A final row totals each reason, and a box at the bottom records the single cause chosen for the next two weeks.

Open a blank worksheet to print

Questions owners ask

What counts as spindle utilisation?

It is the time the spindle is cutting, divided by the time the machine was available. Some shops count any powered time. Pick one meaning and keep it, so trends are fair.

Do we need machine monitoring to start?

No. Operator bookings against a card or a tablet are enough to find the biggest gaps. Monitoring helps later by removing guesswork about short stops.

Why do operators forget to book stoppages?

Booking takes effort when the screen has many choices. Keep the reasons to six or seven, put them at the machine and review the data with the operators so they see it is used.

Should we start with the worst machine?

Start with the machine that runs the most repeat parts. Repeat jobs let you compare setups month to month and show the effect of a fix.

Browse all guidesBack to top ↑