A job card gets filled in when it asks for little, in the order the work happens, with one row per operation. Each row carries machine, operator, start, stop, good quantity, rejected quantity, reason code and a handover signature that the next operator countersigns. Keep the boxes large.
Why operators skip the card
Cards fail for ordinary reasons. The boxes are too small for a gloved hand, the fields come in the wrong order, and half the questions suit the office. A cabinet maker cutting panels and a CNC shop turning shafts both see the same pattern of blank rows and rounded times by Friday afternoon.
Designed for the planner’s desk and not the workbench, the card gets filled at shift end from memory, with times rounded and rejection counts guessed. It records what the supervisor expects. It misses what happened.
- Boxes too small to write in
- Fields ordered for the office
- Questions the operator cannot answer
- Card collected only at shift end
Build the card around one row per stage
Head the card with job number, part, drawing revision, order quantity and due date, then give each operation its own row: cutting, turning, milling, deburring, plating and inspection.
Each row holds machine, operator, start time, stop time, good quantity, rejected quantity and reason code, and one signature closes it once the count is final. Seven fields is the ceiling. No more.
On a cabinet job the rows might read panel saw, edge banding, drilling, assembly and finishing, while a machining job runs facing, rough turning, finish turning and thread rolling.
- Operation name printed in sequence
- Machine and operator
- Start and stop times
- Good and rejected quantity
- Reason code for rejection
- Signature to close the row
Make the handover explicit
The costliest gaps sit between stages. A tray of turned parts waits at the milling bench with no note on what it holds, and nobody knows whether the count is the good count.
Wrong counts between a lathe, a deburring tumbler and the inspection table are the commonest dispute on the floor, and nobody can settle them afterwards. So the handover box at the end of every row states quantity passed, who received it and where the tray was left.
The next operator signs before starting, so a mismatch is caught that minute and not at dispatch, when the lot is already packed and the truck is waiting. Use a heavier border on the box. Where a part waits for a gauge check, add a hold line for the inspector’s initials, so a tray never moves on before the first piece is measured.
Trial it with one line and one supervisor
Pick one product line and print the card for a single week, asking the supervisor to collect it at each handover instead of at shift end. Then walk the floor and watch an operator fill it in, using a normal batch and not a showcase order.
Note how many times the supervisor has to chase a blank row, and write down which box was blank each time, since repeats point at one box. Hesitation means the field is unclear.
Strike out anything nobody uses, enlarge anything that is hard to write, and ask two operators from different shifts to try the revised card. A card that works for the day shift and fails at night has a lighting or reach problem, not a design one.
- Time to fill one row
- Fields left empty
- Fields filled wrongly
- Operator comments after day three
Move to a screen only after the paper works
Paper must work first. Once the layout works on paper, the same rows can be entered on a shop floor screen or picked up by scanning a barcode printed on the card.
A pen on a string helps. Keep the paper layout as the screen layout, because operators already know it, and print the draft this week to test it on one machine before changing anything.
Add the barcode last. Wait until operators stop asking where each box goes, because a barcode printed on a confusing layout only speeds up the confusion.
Stage-wise job card template
A single A4 card turned sideways, with a header carrying job number, part, drawing revision, order quantity and due date. The body has one row per operation, with machine, operator, start, stop, good quantity, rejected quantity, reason code and signature. Each row ends with a handover box.
Open a blank worksheet to printQuestions owners ask
How many fields should a row have?
Seven or fewer fields. Operation, machine, operator, times, good quantity, rejected quantity and signature cover most shops, so add a field only when someone uses it weekly. Drop any blank field after a month.
Should operators write times or does the system?
Writing start and stop is simplest on paper, but operators round to the nearest quarter hour, so the recorded times drift away from the real cycle times. A screen or a barcode scan can stamp the true times automatically, which removes the rounding and the end of shift guesswork.
What about jobs that go outside for plating?
Give outside processing its own row with the vendor, date sent, date received and quantity back, plus the vendor’s lot reference for the return. That keeps the card whole.
Who collects the card?
The supervisor, at each handover. Collecting only at shift end brings back the guessed numbers and rounded times that the card was designed to remove.