Plan seasonal toy production by turning dealer forecasts into units per item, then into mould hours and sewing hours. Work backward from packaging lead times to a fixed start date. Hold a small buffer. Review weekly as orders firm up.
Gather dealer forecasts into one sheet
Ask each dealer and distributor for a forecast per item, not per category. A dealer who says plush will do well has told you nothing. A dealer who wants a given count of a particular teddy in two sizes has given you something to plan against.
Put every forecast in one sheet, with the dealer, the item, the pack and the date they need stock on shelf. Mark which numbers are firm orders and which are hopes. Treat the hopes with a discount based on how that dealer performed last season.
Short notes help. Record whether the dealer also stocks a rival range, because a dealer who splits shelf space between two brands usually orders less of each than the first forecast suggests.
- Item code, pack type and colour
- Dealer, town and required shelf date
- Firm order or forecast
- Last season’s sell through for that dealer
Convert units into mould and sewing hours
Building block ranges run on injection moulds. Divide the units needed by the cavities in the tool, multiply by the cycle time and add changeover and colour purge time. The result is machine hours, and it tells you whether the tool can finish before the rush.
Plush ranges depend on cutting, stitching, stuffing and finishing. Count the stitching stations and the hours each can give. A single bottleneck, often the stuffing table or the final eye fitting, sets the weekly output.
Add the hours up per resource. Where the total exceeds the calendar, you have a decision to make.
Work backward from packaging lead times
Colour boxes, window cartons, blister cards and instruction leaflets often take longer than the toy itself. Printing needs an approved artwork file, a plate or die and a drying and cutting slot. Late artwork approval is a common reason a finished toy waits in a store.
Set the packaging order date first, then the production start, then the sampling. Allow time for the safety test report on any new item, since a toy without it should not ship. Ask your lab how long it takes and add a margin.
Packaging gaps hide easily. Check inner cartons and barcodes as well. A missing barcode label on the day of dispatch can hold a whole truck, and a shortage of master cartons stops a packing line mid shift.
- Artwork approval date
- Die or plate readiness
- Printing and cutting slot
- Safety test report for new items
- Barcode labels and inner carton supply
Protect against changes in demand
Forecasts move. A cartoon release, a viral video or a competitor stockout can double demand for one item overnight while another sits unsold. Keep a modest buffer of raw material that serves several items, such as common colour granules or base plush fabric, rather than stock of finished toys.
Agree a freeze date after which new orders go into a second wave. Dealers accept this when they hear it early. Late additions to a running plan cause changeovers that cost more machine hours than they add output. Colour changes on a block mould need purging, and each purge wastes granules and time.
Review the plan every week
Meet for thirty minutes each week with sales, stores, the moulding supervisor and the packing lead. Compare orders received with the plan, produced against scheduled and packaging due against arrived. Change only what the numbers support.
Keep a list of items that sold out and items that stayed on shelf. Next season it becomes the starting point for your forecast conversation with every dealer. This week, put the dealer forecasts into one sheet and mark each as firm or hope.
Pre season toy plan
A single planning page, one row for each item. Columns show dealer forecast, firm orders, units to make, cavities, cycle time and mould hours, or stitching and stuffing hours for plush. Further columns give packaging order date, artwork approval, test report status and the production start date. A bottom block totals hours per resource against available hours.
Open a blank worksheet to printQuestions owners ask
When should seasonal planning begin?
Start when packaging lead times and the longest mould or sewing run, added together, reach back from the shelf date. Work that arithmetic first and you will see how early the first dealer conversation must happen.
How do we avoid overbuying raw material?
Prefer materials that serve several items, such as common colours and base fabric. Commit to item specific parts like printed boxes only when orders are firm or the forecast is strong.
What if a mould breaks during the rush?
Keep a record of mould condition and last service date, and a spare insert or a tool shop contact for urgent repair. Inspect high volume tools before the season starts.
Should plush and building blocks be planned together?
Plan them on one calendar but separate resource sheets. They compete for packing staff and dispatch space, even though moulding and sewing capacity do not overlap.