Turning a revised OEM schedule into a plan for a Pantnagar supplier

Ganesh HSStrategy and Technology, GullySystem
Practical advice · 5 min read

In this guide 6 sections
The short answer

Treat each revised OEM schedule as a fresh input, not an edit to last week’s sheet. Record the revision, check raw material cover, load machines shift by shift, add a rejection allowance, and publish one plan. Production, stores and dispatch then work from the same numbers.

Capture the revision before anyone reacts to it

The schedule arrives as a PDF on email, a download from the OEM portal, or a forwarded WhatsApp image. Someone copies the quantities onto the whiteboard. That is where the first error creeps in. It rarely gets caught.

Log the revision instead. Note the part number, the drawing revision, the daily or weekly quantity, the date it was received and the revision number from the OEM. Keep the old line visible beside the new one. Never overwrite. A revision history lets you prove to the OEM planner, months later, exactly which quantity you were asked to build on which date and what you committed in reply.

Then see what moved. A pull-in of three days matters far more than a change in the month total. Mark each line as pulled in, pushed out, increased, reduced or cancelled. A supervisor reading the sheet at six in the morning should see the movement without comparing two PDFs by eye.

  • OEM part number and your internal item code
  • Schedule revision number and receipt date
  • Quantity per day, per week and per dispatch slot
  • Change against the previous revision
  • Name of the buyer or planner who sent it

Check raw material cover against the new dates

Explode each part into its bill of materials. A bracket needs coil of one gauge, a casting needs aluminium ingot, a harness needs wire in three colours and a crimp terminal. Multiply by the revised quantity.

Compare against stores stock, open purchase orders and the supplier’s promised dates. Short lines are easy to see once the numbers sit side by side. Nobody has to hunt through three files. Good. Add the stores keeper’s remarks on bin stock that is booked against another part, since that quantity is not really free to use.

Flag the items where lead time is longer than the pull-in. Those need a phone call today. Not a note next week.

Load the machines shift by shift

Capacity is not a monthly figure. Shifts differ. A press line runs differently on a night shift with two operators than on a day shift with four. Use the cycle time per part, the die change time and the planned maintenance slots. Include the trial runs for new dies, which quietly eat a night shift on a mechanical press line every few weeks.

Work backwards from the OEM dispatch date. Allow time for inspection, painting or plating at an outside vendor, packing in the returnable bins and the truck run to the plant gate.

When a machine is overloaded, you have only a few honest options. Add a shift, move the job to another machine with a different die, outsource a process, or tell the OEM planner early which quantity you can hold. The last option feels uncomfortable but costs far less than a missed dispatch and a line stoppage at the customer’s plant.

  • Cycle time and die change time per part
  • Shift pattern and operators available
  • Maintenance and trial slots already booked
  • Outside process lead time and transport day
  • Machine or die that is the real bottleneck

Add a rejection allowance before you promise a date

If the OEM wants one thousand good pieces, you cannot plan one thousand. Scrap is real. Each part has its own history of weld porosity, burrs, short shots or dimensional drift. The production log holds it if operators record the defect code honestly. Each part has its own history of scrap, rework and line returns. Pull that history from the production log by part and by machine.

Plan the gross quantity, so that good pieces come out at the right number. A part with a tricky weld or a thin wall needs a larger allowance than a flat blank.

Review the allowance monthly. Compare planned scrap against actual scrap from the rejection sheet. Adjust. If the rejection sheet shows a die wearing out, the plan should quietly carry that cost until the die is repaired.

Publish one plan and replace the whiteboard

The output is one dated plan. It lists part, quantity, machine, shift, material status, dispatch slot. Stores see what to issue. The supervisor sees what to run. Dispatch sees which invoice and gate pass are due.

Keep the plan in a shared system with a change history, so a supervisor can see why Tuesday’s job moved. A whiteboard photo cannot. Test it. Excel can, but only if one person owns the file.

Start next week with one part family. Run the revised schedule through all four steps by hand, note where it slows down, and decide what a shared tool must do for you.

Revised schedule planning sheet

A single page in four blocks. Block one logs the revision: part number, drawing revision, old and new quantity, date received. Block two checks material: bill of materials line, stock, open purchase order, promised date, shortage. Block three loads machines by shift with cycle time, die change and maintenance slot. Block four sets the rejection allowance and gross quantity, then the dispatch slot.

Open a blank worksheet to print

Questions owners ask

How often should a supplier replan after an OEM revision?

Replan on every revision, however small. A small change in a pull-in date can break a material or machine slot. Doing the check each time takes minutes once the sheet exists.

Where should the rejection allowance come from?

Take it from your own production log and rejection sheet, by part and machine. A general rule across all parts hides the difficult ones. Revisit it after each die repair or material change.

Can Excel do this job?

For a few parts, yes, if one person owns the file. It struggles when several people edit it, when revisions pile up, or when stores and dispatch need live numbers.

What if the OEM sends the schedule on a portal and by email?

Pick one as the source of record and log the other against it. Differences between the two should be raised with the OEM planner the same day.