In this guide 6 sections
Build one round sheet per plant that lists each task, its frequency and the reading to record, then link it to tickets. Cover string checks, inverter logs, module cleaning, thermography and earthing. Tie every abnormal reading to a ticket and every part used to the plant, so the next round starts from facts.
Start with one sheet per plant
Plants differ a great deal. A rooftop array on a factory has short strings and one inverter room, while a ground-mounted plant has hundreds of strings, combiner boxes and a transformer yard.
List the assets first. Count the inverters, combiner boxes, string monitoring units, weather station, transformer and earthing pits, because the round sheet follows that asset list line by line.
Each task gets a frequency, a person and a reading to record. A task without a reading is just a walk. Decide who signs the sheet at the end of the round. Decide who reviews it within two days. Without a reviewer, abnormal readings pile up unread and the sheet becomes a ritual.
- Inverters and rated capacity
- Combiner boxes and fuse ratings
- Weather station and pyranometer
- Transformer, breakers and earthing pits
String checks and inverter logs
At each combiner box, record string current and open-circuit voltage for every string, noting irradiance from the pyranometer at the same time. Compare each reading with its neighbours rather than a fixed number. One string a third lower than the rest points to soiling, a loose MC4 connector or a failed bypass diode.
Download the inverter event log at every round. Look for repeated insulation faults, grid undervoltage trips and fan alarms, and note when the firmware was last updated. Check the grounding and surge protection status lights as well. A dead indicator on a surge protector is easy to miss and costly to ignore.
Keep units the same each time. A screenshot in place of a number makes trends impossible to read.
- String current and open-circuit voltage
- Fuse and connector condition
- Inverter alarm history
- Fan and filter condition
- Cable lugs checked for heat marks
Module cleaning and thermography
Cleaning frequency depends on dust, bird droppings and rainfall. Record the date, method and water used for each block, then compare generation before and after, so you learn which blocks need washing more often. Over a season this gives you a cleaning calendar based on evidence rather than habit, and a clean number to show the plant owner.
A thermal camera finds hotspots that string readings miss. Walk the plant on a clear day with good irradiance and record the module number, the temperature difference against neighbours and the photo reference.
Raise a ticket for each hotspot. Do not tuck it into a notes column.
Tie every finding to a ticket and a spare
A round sheet that only lists observations is a diary. Each abnormal reading should open a ticket carrying the plant, asset, finding, priority and assigned technician, so that nothing depends on a supervisor remembering. Short, plain titles help. A ticket named string 14 low current at combiner box 3 can be acted on at once by whoever picks it up.
When the technician closes the ticket, he records the parts used, such as a fuse, a connector or a surge protector. Stores then see consumption by plant. They reorder before the shelf is empty, not after the next outage.
This keeps the client report honest. The monthly summary lists rounds done, tickets raised, tickets closed and parts used. Clients read it in a minute.
- Plant, asset and finding
- Priority and due date
- Technician and visit date
- Parts used and quantity
- Photo before and after
Run the first round as a test
Print the sheet and carry it on the next scheduled visit. Note which tasks took too long, which readings nobody could take and which assets were missing. A spare combiner box behind the inverter room is a common miss.
Fix the sheet that same evening. Then load it into a phone form so the next supervisor starts with the improved version. Share it with the client’s site contact too. They often spot an asset or a gate rule that your team has missed.
Plant round sheet
A one-page round sheet with a header for plant, date and technician. Blocks follow: string checks with current and voltage columns, inverter log with alarm count, cleaning record, thermography hotspots, earthing readings and a ticket raised column. A footer lists parts used and supervisor sign-off.
Open a blank worksheet to printQuestions owners ask
How often should strings be checked?
Monthly for most plants, with a quicker comparison from the monitoring system in between. Plants in dusty areas may need a check after every cleaning cycle, since soiling hides faults.
Is thermography needed at every round?
Not at every round. Many plants do it a few times a year, or after any unexplained generation drop, using a thermal camera on a clear day.
What should the technician record on closing a ticket?
The cause, the work done, the parts used with quantity and photos before and after. That record feeds the spares plan and the client report.
Can the round sheet work without a signal on site?
It can, if the phone form stores entries offline and syncs later. Test this on the plant’s weakest corner before you choose any tool.