Skip to main content
GullySystem

Project Management for Jobs, Sites and Job Costing

Project management software tracks tasks, timelines, resources, hours, site documents and reports for interiors, civil work, fabrication, AMC sites and IT projects. Seven modules end with cost set against the quote.

Where job costs go unchecked

On a busy site, nobody sets the quoted figure beside what has been spent since the second week. The overrun shows up after the job closes.

  • Decisions taken in a group chat with no owner or date
  • Two sites promised the same crew for one morning
  • Work cut to a drawing replaced days earlier
  • Hours billed from a figure worked out on Friday

Seven modules for running jobs

Begin with tasks and timelines. Costing follows once hours and material are entered.

Task management

Each piece of work has one owner and one due date, filed under the client or project so that nothing floats free.

Project timelines with Gantt charts

Stages sit on a calendar together with what each one is waiting for, such as a drawing, a delivery or a payment. Move one date and the rest move.

Resource allocation

It shows who and what is free before a date is promised. A double booking is refused.

Time tracking and attendance

Hours are booked against the task and the client, billable or not, and the invoice is raised from what was recorded. Attendance covers office staff and site labour: who came in, when and where.

Project document management

Drawings, approvals and site photographs are filed per project, each carrying a version number.

Project management reports

Quoted against spent, and stages running late with the reason, are built while the job is still running.

Made for sites

The screens assume a supervisor on a site with one hand free, not only a laptop and a desk.

  • Site photographs uploaded from a phone, dated and filed
  • Attendance marked at the site, for labour and for staff
  • Stage bills raised from the timeline as each stage closes
  • Variations recorded, so extra work is not missed at billing

What project software cannot do

Software shows a delay and does not shorten one. Where the plan on screen stops matching the site, nobody is updating it, and no feature fixes that. Name the person who owns the plan before starting.

A fit-out job from site visit to final bill

A fit-out for an office shows how project software is used across weeks. Different people touch the job at different stages, from the first measurements to the final bill. Each moment below adds to the record. Follow one job through.

The first site visit

A supervisor visits the site and takes measurements and photographs. They are uploaded from the phone and filed against the project. The quote is linked to the job. Later spending then has something firm to be compared with.

Planning the stages

The project manager lays out the stages on a timeline and assigns crews. Carpentry follows partitions, and painting follows carpentry. If two jobs claim one crew on one morning, the clash is visible before it happens.

Daily site entries

Each evening, the supervisor marks attendance, records hours and uploads photographs. A change requested by the client is logged as a variation. Nothing is forgotten. Extra work is on record when billing time arrives, and the client sees it.

Closing and billing

When a stage is complete, the manager raises a stage bill from the timeline. At the end, cost against quote is reviewed on one screen. The owner learns where money went. The next quotation is built with those lessons in hand.

Points to settle before the first job is entered

Project records are useful only when everyone fills them in the same way. They fix what is tracked, who enters it and what counts as complete. None is hard.

What counts as a stage

Agree how a job is broken into stages, such as demolition, carpentry, electrical and finishing. Use names the crews say aloud. Stages stay the same across jobs, so reports from different sites can be compared with confidence.

Who enters hours and costs

Decide whether supervisors enter hours daily or office staff do it from sheets. Daily entry is more accurate. Whichever is chosen, one person is named for each site and each week, so a missing entry points to someone.

How variations are approved

Extra work must have a rule. Does the client sign, or does the manager approve by message? The record keeps the approval beside the variation, so the final bill is not argued over afterwards by either side of the table.

Subcontractors and material on a running job

A job’s cost is what other people supply: crews from a contractor, boards from a dealer, fittings from a shop. Without a job name on each supply, costing becomes guesswork. Bills come late. Each one is booked to the job the day it arrives.

Subcontractor work booked by stage

A painting contractor’s crew is entered against the stage they worked on, with the days and the agreed rate. Their bill is checked against that record. If it is higher, the difference is visible before payment.

Material issued against the job

The store issues boards, paint and fittings with the job name on the slip. Cost flows into the job as the material leaves the store. Nothing waits for month end.

Surplus material sent back

Leftover tiles and cable go back to the store with a return slip. The job is credited for what returns. Without this step, a job pays for material that sits unused in a storeroom, and the next job buys the same thing again.

Rate changes after the quote

Dealers change prices. Enter the new rate with its date, so earlier issues keep the old figure and later ones take the new. Cost against quote then shows the real effect of the change on that job.

Make an informed decision

Agree the evidence before signing off this part.

Use a representative scenario to decide what this part of the system must show and where review is still needed.

Time tracking and attendance

Can a correction be traced to the right date and session?

For “Time tracking and attendance”, check a late correction against the original register. Agree who may amend it and which downstream total should change after the correction.

Background reading: Frappe HR: attendance records

Where job costs go unchecked

Does a profitable-looking job include work that has not been billed?

Review an unfinished example in “Where job costs go unchecked” with the person responsible for costs. Compare committed work and recorded effort with the amount invoiced before judging the margin.

Background reading: ERPNext: project costing

FAQ

Frequently asked questions

Is this project management software for construction or for IT projects?

Both, set up differently. A civil job runs on stages, drawings and stage bills. An IT project runs on tasks, hours and a monthly invoice. The modules are configured around whichever you are.

Can we see whether a job made money before it finishes?

Yes, once hours and material are booked against the job. Cost sits beside the quoted value from the start, so a job going wrong shows early. It depends on people entering what they spend.

Do the workers need to use an app?

No, not usually. A supervisor marks attendance for a gang, uploads the site photographs and closes the stage. Engineers and office staff use it themselves, because their hours are what the client is billed for.

How does it handle a client who keeps changing the scope?

Each variation is recorded against the project with a date and the requester’s name. The old plan stays beside the new one. When the final bill is questioned, the trail is on screen.

Talk to us

Tell us what you need.

Tell us what your team does today, where work gets stuck and what you want to change.

What happens after you share your requirements

  1. We review your brief and the systems you already use.
  2. We clarify the workflow, missing information and the work to consider first.
  3. The proposed scope sets out the deliverables, responsibilities and dependencies.
  4. Review the scope and commercial terms before deciding whether to proceed.

Start with your requirements

Describe your current process, the people involved and the change you need. Start with the details you know; we can clarify the rest together.

Share your requirements