Scope change request log for software projects
The change request log records each scope change with its estimate, its requester and its approver. Work asked for on a call or in a chat no longer disappears into the project. Once approved, a change raises the budget and the billable total together, and it reaches the next invoice as its own line.
Requester, approver and builder on a change
A change request passes through three kinds of people before anyone writes code. The client asks. The account side approves, and the team builds. The log shows each of them only what they act on.
What one scope change leaves on file
Each change entry is a small contract. It sits inside the big one and names what was asked, what it costs and who agreed. Everything needed to defend the extra charge later is written at the time, not rebuilt at invoice time.
A client call that adds a report
Scope change starts in conversation. A form comes later. A client mentions an extra report on a call, a developer says it is easy, and the afternoon is gone. It is opened at the moment of the ask, before any code exists.
Scope change rules to fix before first entry
Change control fails when nobody agrees what counts as a change. Rules come first. A few written before the first entry save arguments later with the client and inside the team. Agree them with the account owners and delivery heads.
What the change log does not decide
It records and routes a change. It does not decide whether the change is fair. Nor does it judge whether the change falls inside the spirit of the contract, or whether to absorb it as a gesture to the client. Those choices stay with the account owner and the founder. Contract law and tax on the extra charge stay with an adviser. A project with one small deliverable can track changes in email.
Where an approved change travels next
Several other screens are touched at once by an approved change. The plan gains the new milestone or sprint. The budget and billable total rise. Timesheets get a task to log against, and invoicing gets a separate line. No entry is repeated by hand. Its estimate uses the same rate card as the proposal.
- Contract rate applied from Client and statement of work register
- Added work appears on Project plan and milestones
- Hours logged against the change in Timesheets against the plan
- Approved amount becomes its own line in Milestone and time-and-materials invoicing
- Change totals appear by client in Project margin and cost report
Frequently asked questions
Does a declined change stay on the project?
It stays on the log marked declined, with the reason typed in. It adds nothing to either figure. If the client returns to it later, the earlier estimate is there to start from, so nobody sizes it twice.
Can the client see the change before billing?
On the client side, the contact sees the change and its estimate before approval. After approval, the invoice shows it as a separate line. No amount arrives unseen. A question about a line is answered from the entry.
What if the estimate for a change is wrong?
A too-small estimate that was approved is a conversation. The delivery head raises a second entry or revises the first with a new approval. No figure is edited on the quiet. Either way the client sees the new figure before it is billed.
Can an engineer raise a change request?
An engineer who notices extra work can draft the entry, but approval stays with the account owner and the client contact. Who may draft is set up for each project type. A draft is not billable. It does not alter the budget.
Do fixed-bid and time-and-materials projects use it alike?
Both use the same entry. On a fixed bid the change raises the quoted price and effort. On time and materials it raises the hour budget and the expected spend. The approval steps are the same for either.
How this feature fits the system.
Software Development Company Management Software: the parts that work with this feature, the trades that use it and the ways to put it in place.
Client and statement of work register
Each signed statement of work is stored with its billing model, rate card and renewal date, so contract terms can be searched across clients.
Contract ManagementProposals and estimates
An estimate is priced by role and week from the rate card, every revision is kept, and the accepted version opens the project.
Quote & Proposal ManagementProject plan and milestones
Sprints and acceptance dates sit on one calendar per project, and each milestone shows the amount that falls due when the client signs it off.
Project Timelines with Gantt ChartsTell us what you need.
Tell us what your team does today, where work gets stuck and what you want to change.
What happens after you share your requirements
- We review your brief and the systems you already use.
- We clarify the workflow, missing information and the work to consider first.
- The proposed scope sets out the deliverables, responsibilities and dependencies.
- Review the scope and commercial terms before deciding whether to proceed.