Permits and outage approvals for utility crews
Wayleaves, road openings, isolation slots and shutdown windows each carry a requester, an expiry date and the order they support. This feature holds them together and warns the planner before one lapses. Planners book them and foremen check them. A crew is sent only when the paper allows it.
Who needs warning before a permit lapses
A lapsed road opening stops a crew in the street, so the warning has to reach the right person. The planner holds the booking. Foremen act on it, and the yard and the owner follow behind.
Fields behind a wayleave, road opening or isolation slot
Each approval comes from a different office and carries its own limits. Wayleaves come from landowners, road openings from highways authorities and isolation slots from network control rooms. The record keeps what each says and who asked for it.
A road opening, followed from request to expiry
A cable replacement under a main road needs a road opening, a wayleave across private land and an isolation slot. The planner tracks all three. This follows them from request to the day one runs out. Every step leaves a note.
Approval questions to settle before go-live
Permits look like paperwork until a crew is turned away. These choices fit this feature and this trade. Agree them with the planning desk and the foremen before the first approval is entered.
The edge of permit tracking for line crews
This feature records approvals and warns about expiry. It does not issue them or file anything with an authority. Whether a wayleave is legally sound is a question for the firm’s adviser. Traffic management design and safe isolation procedures stay with the people qualified to set them. Renewals still need a phone call. A firm with one annual road permit and a single crew can use a diary.
Permits as they meet the other features
A permit is never alone. It supports an order, holds or releases a crew and affects when materials can be drawn. Its dates and requester come from the order, and what it says flows into the plan. These are the handoffs that count for a crew in the street.
- Work order intake supplies the order each permit supports
- Crew and vehicle scheduling holds crews for approved windows
- Fault and emergency calls log urgent isolations apart from planned ones
- Site records and as-built packs file the permit copy
- Equipment and safety records link the briefing to each shutdown
Frequently asked questions
Which approvals can be tracked for a single job?
Wayleaves, road openings, isolation slots and shutdown windows are all held as permits, each with a type, an issuing office and dates. One order can carry several at once. Traffic management plans can be listed in the same way.
Does it warn the foreman as well as the planner?
The warning goes to the planner, who holds the booking and knows the issuing office. A foreman sees the permits on the order from the phone before leaving. Chasing an office is not a foreman’s job. Settling any lapse falls to the planning desk.
Can one permit support more than one order?
A single road opening may serve several jobs along the same street. Each order is linked to it. When the permit runs out, the list shows every order it was holding up. No job is missed.
What if an outage window is moved by the control room?
Whoever holds the booking edits the window against the order and then moves the crew booking to match. The old date is replaced, so the foreman sees only the current one. Telling the crew is still a phone call.
Does the system apply for permits on our behalf?
Applications are made by the planner to the issuing office in the usual way, and the request is recorded here. The system tracks what was asked, from whom and when it ends. Filing with an authority is not automatic.
How this feature fits the system.
Utility Contractor Management Software: the parts that work with this feature, the trades that use it and the ways to put it in place.
Work order intake
Each order from a network owner is logged with scope, location, priority and target date, and tied to the schedule of rates that governs its bill.
Work Order ManagementQuotations and tender pricing
Tender prices are built from the firm’s own item rates, every revision is kept, and open, won and lost quotations stay in one list.
Estimate/Quotation ManagementCrew and vehicle scheduling
Linemen, jointers, drivers and vehicles are placed against each day’s orders, so free capacity is visible when an urgent fault call comes in.
Technician SchedulingTell us what you need.
Tell us what your team does today, where work gets stuck and what you want to change.
What happens after you share your requirements
- We review your brief and the systems you already use.
- We clarify the workflow, missing information and the work to consider first.
- The proposed scope sets out the deliverables, responsibilities and dependencies.
- Review the scope and commercial terms before deciding whether to proceed.
Start with your requirements
Describe your current process, the people involved and the change you need. Start with the details you know; we can clarify the rest together.
Share your requirements